WATER DISTRIBUTION NETWORK RENEWAL

Water Distribution Network Projects- LEVIDI, ARCADIA, GR


The last decades, the area of Levidi was facing water supply problems due to an old water  distribution network operating in the area.

The water availability had significant fluctuation between 280 – 700 m3/day, due to insufficient water sources during summer months.

The presence of uncharted distribution network imposed the risk of cross-contamination, significant losses and low pressure supply for consumers.

Hydrobalance’s design team reviewed the special operating circumstances and presented ways of overcoming the special challenges through hydraulic modelling and smart network design.

The existing main and secondary water distribution network was replaced in its entirety.

Our focus was to implement the minimum route changes, in order to sustain the existing operational  area division for the network. Each supply zone has distinctive operating conditions and was supplied by one reservoir .

PE pipes were chosen due to their flexibility, strength  and ease of implementation and transport.

Hydro Balance - Σύμβουλοι Μηχανικοί | Υδραυλικές Μελέτες Δημοσίων & Ιδιωτικών Εργων

2017

Project starts

2.2m €

Project construction funding, part of a bigger scheme for water distribution network renewals

22km

Total pipe length to be replaced

KEY POINTS

Technical

Design of water mains to replace ageing assets. Full Water Networks Hydraulic Modelling and desktop assessment

Money

Support the local economy and tourism

Life Cycle

Network operation to last 40 years

Design Duration

Project was completed within 5 months

Value

Provided the client with a minimally invasive solution with respect to the community’s water needs

Compliance

In accordance with the national legislation

Environment

The scheme ensured the water security and water leakage prevention